28th PDWP

ENVIRONMENT SECTOR                             

Capacity Building of EPA Punjab for Enforcement of Environment Standards in Punjab including Combined Effluent Treatement Plants (CETPS) and Industrial Estates (IES) under J&C Program.

Cost: PKR 387.598 million| Status: Deferred

ENERGY SECTOR                                         

Updating of Feasibility Study, Preparation of PC-I, Management of Bidding Process on EPC Mode and Construction Supervision of 15-20 MW Biomass Thermal Power Project near Chak Jhumra, Faisalabad (PC-II).

Cost: PKR 165.000 million| Status: Approved

ROADS SECTOR                                            

Manufacturing / Installation of Gantries on KPRRP Roads Phase-I, II & III for Chief Engineer (North / South Zone) Punjab Highway Department.

Cost: PKR 1134.277 million| Status: Deferred