The PDWP Approved Twelve Development Schemes of Various Development Sectors

The Provincial Development Working Party Punjab approved twelve development schemes of various development Sectors with an estimated cost of PKR. 59,057.572 Million.

These schemes were approved in the 4th meeting of Provincial Development Working Party (PDWP) of current fiscal year 2015-16 presided over by the Punjab Chairman P&D Board Muhammad Irfan Elahi. Members of the Planning & Development Board, Provincial Secretary concerned and other senior representatives of the relevant Provincial Departments also attended the meeting.

According to Spokesman for P&DD, the approved development schemes included:

  • Punjab Police Integrated Command, Control & Communication (PP-IC3) Programme at the cost of PKR. 13,387.679 Million 
  • Preservation and restoration of Shahdara Complex of Monuments (Revised)at the cost of PKR. 467.990 Million
  • Lahore Ring Road Project – Southern Loop (Package-1) (Land Acquisition and Relocation of Utilities) at the cost of PKR. 5425.595 Million
  • Lahore Ring Road Project – Southern Loop (Package-2) (Land Acquisition and Relocation of Utilities) (Revised) at the cost of PKR. 9956.594 Million
  • Lahore Ring Road Project – Southern Loop (Package-3) (Land Acquisition and Relocation of Utilities) at the cost of PKR. 5820.664 Million
  • Lahore Ring Road (Package-9) Construction of Interchange at Harbanspura Canal Crossing (Revised) at the cost of PKR. 2376.215 Million
  • Improvement/rehabilitation of existing Multan Road, Lahore from Thokar Niaz Baig to Chauburji (Proposed Sewerage Drainage and Water Supply System) Package-III. (Revised) at the cost of PKR. 2045.751 Million
  • Rehabilitation/widening of 10’-12’ rural roads under “Khadem-e-Punjab Roads Programme (KPRP)” (South Zone) at the cost of PKR. 8025.058 Million
  • Khadem-e-Punjab Roads Program (KPRP) (Rehabilitation and Widening of (Rural) Roads in Punjab Highways Department, North Zone) (Umbrella PC-I) (Revised)at the cost of PKR. 9892.000 Million
  • Widening/improvement of road from Ouderwal to Nila Road length: 43.00 km District Chakwal at the cost of PKR. 782.995 Million
  • Topographic Survey and geotechnical studies for land slinding zonization of Murree Hill area mainly located between old Rawalpindi – Murree Road and Islamabad Murree Expressway in Murree (amended) at the cost of PKR. 50.000 Million
  • Establishment of Directorate General of Monitoring and Evaluationat the cost of PKR. 827.031 Million