The 48th Meeting of the Provincial Development Working Party (PDWP)

Tuesday, March 26, 2024

The 48th meeting of the Provincial Development Working Party (PDWP) held under the Chairmanship of Chairman P&D Board Barrister Nabeel Ahmad Awan and approved various development schemes with an estimated cost of Rs 72000.997 million

The approved schemes are as follows:

1) Channelization of Jabba Nullah Tehsil & District Mianwali at the cost of Rs 960.456 million

2) Concrete Lining of Maggi Magassom Link RD 0 to 58500 at the cost of Rs 420.263 million

3) Rehabilitation of 6R/Hakra with System at the cost of Rs 461.283 million

4)Rehabilitation of 7R/Hakra with System at the cost of Rs 414.936 million

5) National Program for Improvement of Watercourse In Pakistan (Punjab component) Phase-II at the cost of Rs 47503.49 million

6) Replacement of Beds and other Equipment at RHCs of Punjab at the cost of Rs 1342.338 million

7) Program for Provision of CT Scan Service in Selected THQS on Outsourced Model. (Revised) At the cost of Rs 988.917 million

8) Rehabilitation / Improvement of Ferozepur Road from Gajumata to Kasur L=33.00km, Lahore at the cost of Rs 8417.402 million

9) Rehabilitation of road from Kot Radha Kishan to Kasur L=31.00 km, District Kasur at the cost of Rs 2025.990 million

10) Rehabilitation and Carpeting of Metalled Road from Rafiq Chowk to Mehrab Wala Ahmedpur East, Length 21.75 km District Bahawalpur at the cost of Rs 544.383 million

11) Rehabilitation/Improvement of Metalled Road from Kacha Khuh to

Abdul Hakeem Length 20.00 Km, District Khanewal at the cost of Rs 1396.599 million

12) Rehabilitation of Road from Chishtian to Haroonabad via Pull Murad Length 26.40 Km District Bahawalnagar at the cost of Rs 1438.176 million

13) Dualization of Muzaffargarh Road (Jauharabad Chowk Girote), (on-going) Length=25.25 km, District Khushab at the cost of Rs 3460.093 million

14) Rehabilitation of Mana Jamlera Road, Length 16.10 Km District Vehari at the cost of Rs 645.154 million

15) Rehabilitation / Improvement of Lahore Raiwind Road from Lake City to Raiwind, Length 10 Km in District Lahore at the cost of Rs 1957.517 million

16) Feasibility Study and Establishment of Punjab Grid Company. (Revised PC-II) At the cost of Rs 24 million

Secretary P&D Board Dr Asif Tufail, Chief Economist Mr Nasir Iqbal Malik, Members P&D Board, Head of relevant depts and other senior representatives of the relevant provincial departments attended the meeting.